Week of March 24, 2019: Week 59 - As we enter into the 59th week of construction, we can look forward to the following:
Front of the building looking sharp! Main hallway with wall paneling. Classrooms on the 3rd floor nearly complete. Floor and baseboard in place. Hallway flooring being installed. Seats being installed in the auditorium. From the stage looking up. Display case in the main hallway. Pads being installed in the gymnasium. Locker room lockers. On Air! Coolest sign! Deserves the double thumbs up!
Week of March 17, 2019: Week 58 - As we enter into the 58th week of construction, we can look forward to the following:
Cabinets in the art classroom! Hallway flooring being installed! Mirrors, soap dispensers, and paper towel dispenser installed in the restrooms. Media center taking shape! Sound clouds being installed in our auditorium. Outdoor learning space! Dust collector outside our wood shop! Outdoor learning space outside the student union! Our new learning community!
Week of March 10, 2019: Week 57 - As we enter into the 57th week of construction, we can look forward to the following:
Front foyer breakout space! Sound clouds being installed in the auditorium. Auditorium getting prepped for sound clouds and seats. Lines freshly painted in our new gym! Our BMS Eagle painted in the middle of the floor! Mr. Messore, Dr. Dillon, and our BPS PTO Presidents giving double thumbs up!
Week of March 3, 2019: Week 56 - As we enter into the 56th week of construction, we can look forward to the following:
Shared classroom on the first floor! Hallway that runs behind the larger break out space. Teacher workroom. Circulation desk in the media center. Auditorium getting ready for seats! Gymnasium striped! Kitchen servery! Kitchen! Our new building on a snowy day! Mrs. Bulk and I giving the double thumbs up from the gallery bridge connecting the media center and the auditorium.
|